There's not much to report today.  In a little while I'll run out to the house to see if the painters are at work.  However, "watching paint dry" doesn't make for informative photos.  Instead, being about two weeks from completion, I thought it might be interesting to look back at the construction process to date.  This post covers 2010; tomorrow's will cover 2011.

May 30 — My last Sunday at St. John's, Grand Haven.
June 1 was my first day as a retiree.
July 26 — The lot is being cleared of trees.
July 29 — Kyle and Dave site the house on the lot.
August 25 — Jim's crew lays out the footings in R.J.'s hole.
August 30 — The footings have been poured.
September 17 — The foundation has been built,
and R.J. and Kyle site the garage.
September 21 — Framing starts.
October 5 — Kyle, Dave and Jose work on the porch beam.
October 13 — Jose nails in the SIS panels.
October 25 — The house is roughed in and roofed.
October 27 — The first windows are installed.
November 11 — Work begins on the siding.
November 23 — Remaining windows are installed,
interior framing and basic plumbing is finished.
December 1 — The well is drilled.
December 6 — Heating system is installed.
December 23 — The house has been wired and insulated.
December 28 — Drywall is going up.
Tomorrow, a look at progress during the new year. •••