Thursday, October 7, 2010

Do It Yourself

The original plan was that a crane would appear this morning (Thursday) at 8:00 to lift the trusses for the 2-story section into place.  But yesterday Kyle decided that a do-it-yourself approach would work better.  So, using a rope, the trusses were hauled up and muscled into position, all in about 45 minutes.

Sean, Dave and Kyle get ready to lift the last truss into place.
The crew nails in that last truss.
The "Kyle Krane."  Patent pending.
Once the trusses were in place, Kyle used the Bobcat to bring a load of plywood over to the south roof and lifted it up to the roofline.  Jose and Dave then brought the plywood in through the window in the future master bedroom.  From there the sheets went up through the rafters to become the roof deck.
Kyle lifts 20 sheets of plywood for the roof deck...

... and Jose and Dave haul them in through the window.
Kyle and Sam nail down the plywood.
Kyle wrestles another sheet through the rafters.
Dave gets ready to cut a sheet of plywood for the roof.
Kyle surprised me by noting that yesterday was the ninth day of framing.  I am really pleased with how quickly the work has gone, some rainy days notwithstanding.  The house and garage seem to have sprouted out of the earth like mushrooms!

The garage is fast taking shape.
Sam did not like working over the stairwell.  "It's a long way down, sir."
Sean (legs showing) helps install the roof deck in
what will soon be the guest bedroom.
After nine days of framing, the house is beginning to show
its finished shape.
Now I'm headed back to Southwest Michigan to order cabinets and lighting fixtures. •••